What goes on a risk?
Four notes keep the reasoning with the risk: the consequence, the likelihood, the existing controls and the mitigation actions.
Raise a risk in one panel: what could go wrong, who owns it, who follows up, how bad it would be and how likely.

Raise a risk in one panel. The rating is worked out for you. Linked to related work. Filter the list, export it, and take the report to the risk review. The risk register, linked to submittals and issues.
Dana, the project manager on Harbourview Residences, raises the Level 8 water risk and takes the list to the risk review.
After the sealant gap on Issue #73 comes up at the field review (a site observation in the US), Dana raises “Water intrusion at Level 8 curtain-wall joints” in one panel.
She sets the impact to Major and the probability to Medium. The rating works itself out: MODERATE · 12.
She links Submittal #52, the curtain wall shop drawings, and Issue #73. The link shows on both records, so each one points back to the risk.
Before the risk review, Dana filters the list and exports it as the report for the review.
| THE RISK | CURRENT CONTROL | CURRENT RISK RATING | FURTHER TREATMENT |
|---|---|---|---|
| Water intrusion at Level 8 curtain-wall joints | Joint detail on the approved shop drawings | Moderate | Reseal and water test before finishes |
| Glass delivery for Levels 10 to 12 | Weekly call with the supplier | Major | Hold a second supplier slot |
| Embed plates out of tolerance, Levels 9 to 12 | Embed survey before each pour | Severe | Standard fix detail from the engineer |
| Visual mock-up sign-off, podium glazing | Mock-up booked on site | Moderate | Set the review date with the owner |
App screens redrawn from the web app with Harbourview demo data. The Risk guide on help.aecis.com
Four notes keep the reasoning with the risk: the consequence, the likelihood, the existing controls and the mitigation actions.
Link a risk to related submittals and issues, and to other risks. The issue's Related tab lists the risk.
Comments, files and location tags sit on the risk itself. The notification emails for a risk are kept on the risk, on its Email tab.
Step through the risks in the list from the detail panel.
Start your project and raise the first risk yourself, or book a 20-minute demo and we will set it up on your project with you.