In the same project as submittals and issues

The milestone schedule, in the browser.

The project manager keeps it current in the browser; the project's other roles with read access view it and export it.

  • One Gantt. Forecast, baseline and actual dates, with Critical Path.
  • Dashboard Delay. Derived from the latest milestone end when no manual Delay value is set (a manual value wins).
  • Read-only at the end. Once the project is completed, it turns read-only. It exports to Excel, PDF or MPP XML.

See where the Delay figure comes from

Projects running AECIS
Milestones demo video: on Monday Nov 23 Jordan, the general contractor, sends his schedule update; Dana, the project manager, enters the revised dates; the Level 8 curtain wall install sits past its baseline; Critical Path shows the chain to Turnover to owner; the schedule goes out as a PDF; and at the refresh the Dashboard's Delay reads 2 days ahead
One Monday on Harbourview Residences: the general contractor's update, the revised dates in the browser, and Critical Path. It plays muted; turn the sound on for quiet guitar.

The project's milestone schedule, in the browser. In the GC's own schedule, the Level 8 curtain wall moves later. The project manager enters the GC's revised dates. Critical Path highlights what would push the project end date back. Before the owner meeting, the project manager exports the schedule to PDF. Delay is derived from the latest milestone end.

One revised date, from the general contractor's update to the Dashboard

Monday, November 23, on Harbourview Residences: Jordan, the general contractor (GC), sends his schedule update, and Dana, the project manager, enters the revised dates in the milestone schedule.

The GC's update moves Level 8

In the GC's own schedule update, the Level 8 curtain wall install moves later.

Revised dates, entered in the browser

The project manager enters the revised forecast date in the browser; the parent rolls up at once.

Past its baseline, on the Critical Path

With the baseline on, the bar sits past its slate baseline. Critical Path highlights it in red.

The Dashboard's Delay, at the next refresh

The project manager enters the revised turnover date too. The Dashboard's Delay, derived from the latest milestone end when no manual Delay value is set (a manual value wins), changes at the next refresh. Before the owner meeting, the project manager exports the schedule to PDF.

One milestone schedule, each from the angle of their work
DanaProject manager, owner's side

Enters the revised dates from the GC's update.

JordanGeneral contractor (GC)

Checks the Level 8 install on the Critical Path.

SamCurtain wall sub

Plans his crew for the Level 8 window.

MeiEnvelope consultant

Follows the curtain-wall rows for her field reviews (site observations).

AlexOwner

Reads Turnover to owner and the Delay figure.

Every role on the project reads the same schedule and can export it; the Project Manager role adds and edits.

Feeds the Dashboard

Once a Grand Opening date is set, the Dashboard's Delay figure is derived from the latest milestone end when no manual Delay value is set. A manual value wins.

The Delay figure needs milestone read access. Watch the demo

Everyday questions, answered in the schedule

Who can change the schedule?

The Project Manager role adds and edits; Administrators and Project Admins also delete. The project's other roles with milestone read access view it and can export it.

What does the Dashboard's Delay figure measure?

Once a Grand Opening date is set, it is derived from the latest milestone end when no manual Delay value is set: latest milestone end minus the Grand Opening date, in days. A manual value wins. More on the Dashboard

What does Critical Path show?

The milestones whose slip would push the project end date back, highlighted in red.

What happens when the project is completed?

Milestones turns read-only and the edit tools are hidden.

Which files come in and go out?

Export to Excel, PDF or MPP XML; import from MPP XML. Export and import on help.aecis.com

Also included

  • Hierarchy with roll-up
  • Drag-and-drop reorder
  • Four link types with lag
  • Column sort and filter, zoom
  • Holidays and event markers
  • Keyboard shortcuts

Web only, with no mobile version. Schedules import from MPP XML.

Try it before your next owner-architect-contractor (OAC) or site meeting

Start your project and enter the first milestones yourself, or book a 20-minute demo and we will set it up on your project with you.

Before the first milestone

Questions reviewers ask

What owners, consultants, contractors and trades ask most, answered in a line or two.

Still have a question?

The Milestones guide on help.aecis.com covers adding and editing milestones, links, Critical Path and export, or we can show it on your project.

How far does the scheduling go?

Predecessor links with lag, a baseline, and Critical Path to highlight the milestones whose slip would push the project end date back. Detailed scheduling stays in the scheduler's own tool.

Which schedule format imports?

MPP XML.

Where does it run?

In the browser. Milestones is web only, with no mobile version.

Other features

9 features are included in 1 platform - easy access, easy manage your projects.